Yates renovations over budget, New West Theatre Society asks for rent forgiveness
LETHBRIDGE – After touting that the $13.4 million Yates Theatre renewal had been on budget, even while media were given a tour of the nearly-completed facility September 6, city administration revealed at Monday’s council meeting that the project was in fact, over budget by $560,000.
Tony Vanden Heuvel, Director of Community Services, says there was an administrative “oversight” as the documents with the correct numbers were being drafted. He says the overage occurred because the scope of the project was a lot bigger than they have anticipated.
“In the area of asbestos abatement, we had to work with our general contractor on the job to make sure that was all done properly, the requirements met. As a result of opening up the ceiling and finding out about things, some of our design work had to be re-done. So very typical with renovation.”
However, back in January when asbestos was found, and again last May during the third construction delay, when new structural issues were identified, Recreation services Manager Jason Freund told LNN the contingency budget had not been used up yet.