Work continuing on the City’s first ever Bike Boulevard
LETHBRIDGE – Drivers, cyclists and pedestrians will all notice some significant changes taking place on 7 Ave. S as work continues moving along on the City’s first ever Bike Boulevard, including new traffic lights and a reduced speed limit.
The Bike Boulevard is designed to give cyclists priority, and it does that by discouraging drivers from using 7 Ave. S as a through route to travel east and west from 4 St. S to Mayor Magrath Dr. S.
Drivers will instead be encouraged to used 6 Ave. S or 8 Ave. S.
Project Manager Robert Kovacs says the latest addition to the Bike Boulevard is a change to the intersection of 7 Ave. S and 13 St. S.
“Newly installed traffic lights are now on flashing mode, and going down this corridor we have roundabouts set up. We’re also going to have new intersection type installed known as directional diverters. That will remove some vehicular traffic off 7 Ave. S, to encourage more bike traffic through here,” Kovacs said, adding the speed limit has also been reduced to 30 km/h.