Damage to Whoop-Up Drive a bit worse than thought, but still safe
The City of Lethbridge and assessment crews have uncovered more damage to Whoop-Up Drive.
On August 6, 2025, a piece of heavy equipment struck the underside of the bridge. The initial assessment showed damage to four of the six steel girders that support the roadway.
READ MORE: Four of six girders on Whoop-Up Drive damaged, assessments continue (Aug. 12 article)
Acting Director of Infrastructure Jason Drenth explains that they were finally able to look inside the bridge deck, where additional damage was discovered.